Critical stabilisation project

Subsidence rectification under a live coal stacker.

Client / Scope: Anglo AmericanLocation: Moranbah North CHPP, QLD
868m³
Concrete placed
14%
Under budget
3,649
Man-hours
0/0/0
FAC · MTI · LTI

The challenge

  • Stacker sinking along its rail track
  • 3 m work windows, every second pier
  • Live coal cycles — no downtime allowed

The EMS response

  • Staged 2 m excavation under the rail beam footing
  • 900 mm extension cast, every-second-pier sequencing
  • 40 MPa pours timed around live stacking cycles

Value delivered

  • 868 m³ of 40 MPa concrete placed
  • 14% under budget, on programme
  • Zero recordable safety events
  • Repeat scope awarded on adjacent Anglo assets
Civil & Concrete

Pit G second portal entry

A second underground entry, delivered around live operations.

Client / Scope: Anglo American · CAPCOALLocation: Aquila Mine, Pit G, QLD
2nd
UG entry / exit
1,500mm
Beam depth
T16
Structural piles
Follow-on
Awarded

The challenge

  • Second UG entry/exit needed for production continuity
  • Pile caps and 1,500 mm deep beams under existing portal
  • Spec mix, epoxy injection — first-time accuracy required

The EMS response

  • T16 pile caps installed under the existing portal
  • 1,500 mm beams cast with 32 mm bar, 80 mm blinder
  • Hanson PMP/40/20/80 mix to spec

Value delivered

  • Second UG entry/exit delivered to specification
  • Existing structure held without movement
  • Repeat civil scope awarded on adjacent CAPCOAL works
  • Same crew retained for follow-on portal works
Civil & Concrete

Water treatment circular slab

Bespoke circular form, single pour window, finished to spec.

Client / Scope: Dowden’s PumpingLocation: Water Treatment Plant, QLD
Critical
Path scope
Single
Pour window
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • Large diameter slab on critical-path water treatment infrastructure
  • Single pour window — no opportunity to re-pour
  • Bespoke circular formwork had to be built right the first time

The EMS response

  • Pre-pour clean and base course preparation
  • Bespoke circular formwork built and set to spec
  • Reo install across the full slab diameter
  • Single supervised pour with machine finish

Value delivered

  • Slab delivered to specification, on programme
  • Zero recordable safety events across the works
  • QA documentation handed back at completion
  • Repeat scope awarded on adjacent WTP works
Recovery & Vac

Conveyor belt recovery & reuse

Turning end-of-life conveyor belting into practical site value.

Client / Scope: Belt Recovery & ReuseLocation: Collinsville and partner sites, QLD
103
Rolls recovered
306t
Diverted from landfill
0/0/0
FAC · MTI · LTI
ESG
Aligned

The challenge

  • Used belting creates storage and removal headaches
  • Landfill disposal carries cost and environmental impact
  • Belt change-outs leave messy sites with nowhere to send the rolls

The EMS response

  • Removal and collection of waste belting during shutdowns and change-outs
  • Processing of belt material for industrial reuse
  • Repurposing into practical site and industrial applications
  • ESG-aligned reporting on diverted waste volumes

Value delivered

  • 103 rolls recovered — 306 tonne diverted from landfill
  • Support for ESG and sustainability targets
  • Cost-effective waste management alternative
  • Tidier sites during major belt change-outs
Vegetation

Single-pass vegetation management

Single pass. No rework.

Client / Scope: Vegetation ManagementLocation: Callide Basin Mine, QLD
Single
Pass
2× CTL
Kubota SVL73-3
0/0/0
FAC · MTI · LTI
BreatheSafe
Cabs

The challenge

  • Brush and regrowth across mine infrastructure and rehab zones
  • Operating in MIA, haul roads, ROM pads, fuel farms and laydown areas
  • Operator dust and PM exposure to be managed at all times

The EMS response

  • Kubota SVL73-3 High Flow CTLs (×2), full RPM at the attachment
  • Mulcher, HD slasher and stick rake — gearbox-driven, chain-guarded
  • Spray trailers and brush cutters for tight-access detail work
  • BreatheSafe pressurised cabs with positive-pressure filtration

Value delivered

  • Single-pass mulching — no rework required
  • Firebreaks installed and rehab zones cleared
  • Zero recordable safety events across the works
  • Same crew available for follow-on regrowth campaigns
Buildings & Installs

Project building relocation

Disconnect, transport, rebuild. Live mine site, repeat outcome.

Client / Scope: Anglo American · MNCLocation: Moranbah North, QLD
3-section
Building relocated
12×12m
Gable awning
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • Three-section project building to be moved across the MNC site
  • Live mine environment, fixed window, no rework allowed
  • Generator, electrical, plumbing and tie-downs all to be re-established

The EMS response

  • Building disconnected, split into 3 sections and transported
  • Level concrete pads prepped and poured at the new location
  • Building re-erected, sealed and re-flashed water-tight
  • Cyclone tie-downs, 20,000L water tank and gable awning installed

Value delivered

  • Building back in service within the planned window
  • Zero recordable safety events across the works
  • 12 × 12m gable awning and water tank added as a site asset
  • Variation works absorbed without programme impact
Buildings & Installs

Dawson South ERT shed

Skillion shed for emergency response training, slab to handover.

Client / Scope: Anglo American · DawsonLocation: Dawson South, QLD
8×8.2m
Skillion shed
6 piers
+ 100mm slab
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • New ERT training facility needed on a live mine site
  • Civil, structural and electrical scopes under one job
  • Tight footprint between existing buildings and services

The EMS response

  • 6 reinforced concrete piers, 450 dia × 900 deep installed
  • 100mm slab poured with single layer SL82 mesh
  • 8 × 8.2m skillion frame and roof supplied and erected
  • Electrical run from existing board for lights and trickle feed

Value delivered

  • ERT shed delivered to specification, on programme
  • Zero recordable safety events across the works
  • Single contractor for civil, structural and electrical
  • QA documentation handed back at completion
Asset Protection

Burton blast & paint

Ongoing structural blast and paint, in-situ and yard, monthly call-off.

Client / Scope: Bowen Coking Coal · Lenton JVLocation: Burton Mine, QLD
Monthly
Call-off scope
8/6
Roster
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • Live coal-handling assets needing rolling refurb
  • Corroded structural steelwork and coating breakdown
  • Containment of blast media in a live plant environment

The EMS response

  • Encapsulation with brattice to contain media and dust
  • Abrasive blast of structural steel and crusher components
  • Inspect, mark-up and repair defective steelwork
  • Apply protective coating system to spec — EMS-owned plant on site

Value delivered

  • Coal-handling asset life extended
  • Zero recordable safety events across the works
  • Encapsulation kept media and dust off live plant
  • Repeat blast and paint scopes awarded
Buildings & Installs

Grosvenor bathhouse install

Install-only scope on a live site. Civil, structural, plumbing and fit-off.

Client / Scope: Anglo American · GrosvenorLocation: Grosvenor Mine, QLD
Live site
No shutdown
95 posts
+ 64Lm walkway
0/0
MTI · LTI
Follow-on
Awarded

The challenge

  • Footprint sat over live underground services
  • Fire main needed relocating to AS spec
  • Multi-trade scope, single contractor
  • Inclement weather across the build

The EMS response

  • Hydro-ex to locate live services
  • Fire main relocated outside footprint
  • 95 posts and PFC supports installed
  • Modules craned in and fitted off; plumbing and fire connections completed

Value delivered

  • Bathhouse delivered and operational
  • Zero recordable safety events
  • Single contractor across all trades
  • QA pack and engineer sign-offs handed back
Recovery & Vac

Vacuum excavation services

Brand-new mining-spec fleet, ready to deploy across Queensland.

Client / Scope: Vacuum ExcavationLocation: Paget, Mackay, QLD
24/7
Response
Brand-new
Fleet
Mining-spec
Compliant
2006
In market since

The challenge

  • Non-destructive digging around live services
  • Safe and efficient service location
  • Liquid-waste pump out and removal

The EMS response

  • Industrial cleaning of plants and sites
  • Sump and pit cleaning — mining and ports
  • Conveyor and processing area clean-downs
  • Trained crews mobilised from Mackay base

Value delivered

  • 24/7 emergency callout — spill response and clean-up
  • Hazardous waste handling and containment
  • Suited to mining, ports and rail sites