Case Studies

The work spoke for itself.

Thirteen projects across civil and concrete, asset protection, vegetation, buildings and vacuum excavation — delivered safely, on programme, with repeat scopes to show for it.

Civil & Concrete

Critical stabilisation project

Subsidence rectification under a live coal stacker.

Client / Scope: Subsidence RectificationLocation: Moranbah North CHPP, QLD
868m³
Concrete placed
14%
Under budget
3,649
Man-hours
0/0/0
FAC · MTI · LTI

The challenge

  • ✓Stacker sinking along its rail track
  • ✓3 m work windows, every second pier
  • ✓Live coal cycles — no downtime allowed

The EMS response

  • ✓Staged 2 m excavation under the rail beam footing
  • ✓900 mm extension cast, every-second-pier sequencing
  • ✓40 MPa pours timed around live stacking cycles

Value delivered

  • ✓868 m³ of 40 MPa concrete placed
  • ✓14% under budget, on programme
  • ✓Zero recordable safety events
  • ✓Repeat scope awarded on adjacent assets
Civil & Concrete

Pit G second portal entry

A second underground entry, delivered around live operations.

Client / Scope: Portal Entry ConstructionLocation: Aquila Mine, Pit G, QLD
2nd
UG entry / exit
1,500mm
Beam depth
T16
Structural piles
Follow-on
Awarded

The challenge

  • ✓Second UG entry/exit needed for production continuity
  • ✓Pile caps and 1,500 mm deep beams under existing portal
  • ✓Spec mix, epoxy injection — first-time accuracy required

The EMS response

  • ✓T16 pile caps installed under the existing portal
  • ✓1,500 mm beams cast with 32 mm bar, 80 mm blinder
  • ✓Hanson PMP/40/20/80 mix to spec

Value delivered

  • ✓Second UG entry/exit delivered to specification
  • ✓Existing structure held without movement
  • ✓Repeat civil scope awarded on adjacent works
  • ✓Same crew retained for follow-on portal works
Civil & Concrete

Water treatment circular slab

Bespoke circular form, single pour window, finished to spec.

Client / Scope: Circular Concrete SlabLocation: Water Treatment Plant, QLD
Critical
Path scope
Single
Pour window
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • ✓Large diameter slab on critical-path water treatment infrastructure
  • ✓Single pour window — no opportunity to re-pour
  • ✓Bespoke circular formwork had to be built right the first time

The EMS response

  • ✓Pre-pour clean and base course preparation
  • ✓Bespoke circular formwork built and set to spec
  • ✓Reo install across the full slab diameter
  • ✓Single supervised pour with machine finish

Value delivered

  • ✓Slab delivered to specification, on programme
  • ✓Zero recordable safety events across the works
  • ✓QA documentation handed back at completion
  • ✓Repeat scope awarded on adjacent WTP works
Recovery & Vac

Conveyor belt recovery & reuse

Turning end-of-life conveyor belting into practical site value.

Client / Scope: Belt Recovery & ReuseLocation: Collinsville and partner sites, QLD
103
Rolls recovered
306t
Diverted from landfill
0/0/0
FAC · MTI · LTI
ESG
Aligned

The challenge

  • ✓Used belting creates storage and removal headaches
  • ✓Landfill disposal carries cost and environmental impact
  • ✓Belt change-outs leave messy sites with nowhere to send the rolls

The EMS response

  • ✓Removal and collection of waste belting during shutdowns and change-outs
  • ✓Processing of belt material for industrial reuse
  • ✓Repurposing into practical site and industrial applications
  • ✓ESG-aligned reporting on diverted waste volumes

Value delivered

  • ✓103 rolls recovered — 306 tonne diverted from landfill
  • ✓Support for ESG and sustainability targets
  • ✓Cost-effective waste management alternative
  • ✓Tidier sites during major belt change-outs
Vegetation

Single-pass vegetation management

Single pass. No rework.

Client / Scope: Vegetation ManagementLocation: Callide Basin Mine, QLD
Single
Pass
2× CTL
Kubota SVL73-3
0/0/0
FAC · MTI · LTI
BreatheSafe
Cabs

The challenge

  • ✓Brush and regrowth across mine infrastructure and rehab zones
  • ✓Operating in MIA, haul roads, ROM pads, fuel farms and laydown areas
  • ✓Operator dust and PM exposure to be managed at all times

The EMS response

  • ✓Kubota SVL73-3 High Flow CTLs (×2), full RPM at the attachment
  • ✓Mulcher, HD slasher and stick rake — gearbox-driven, chain-guarded
  • ✓Spray trailers and brush cutters for tight-access detail work
  • ✓BreatheSafe pressurised cabs with positive-pressure filtration

Value delivered

  • ✓Single-pass mulching — no rework required
  • ✓Firebreaks installed and rehab zones cleared
  • ✓Zero recordable safety events across the works
  • ✓Same crew available for follow-on regrowth campaigns
Buildings & Installs

Project building relocation

Disconnect, transport, rebuild. Live mine site, repeat outcome.

Client / Scope: Building RelocationLocation: Moranbah North, QLD
3-section
Building relocated
12×12m
Gable awning
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • ✓Three-section project building to be moved across the MNC site
  • ✓Live mine environment, fixed window, no rework allowed
  • ✓Generator, electrical, plumbing and tie-downs all to be re-established

The EMS response

  • ✓Building disconnected, split into 3 sections and transported
  • ✓Level concrete pads prepped and poured at the new location
  • ✓Building re-erected, sealed and re-flashed water-tight
  • ✓Cyclone tie-downs, 20,000L water tank and gable awning installed

Value delivered

  • ✓Building back in service within the planned window
  • ✓Zero recordable safety events across the works
  • ✓12 × 12m gable awning and water tank added as a site asset
  • ✓Variation works absorbed without programme impact
Buildings & Installs

Dawson South ERT shed

Skillion shed for emergency response training, slab to handover.

Client / Scope: ERT Shed ConstructionLocation: Dawson South, QLD
8×8.2m
Skillion shed
6 piers
+ 100mm slab
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • ✓New ERT training facility needed on a live mine site
  • ✓Civil, structural and electrical scopes under one job
  • ✓Tight footprint between existing buildings and services

The EMS response

  • ✓6 reinforced concrete piers, 450 dia × 900 deep installed
  • ✓100mm slab poured with single layer SL82 mesh
  • ✓8 × 8.2m skillion frame and roof supplied and erected
  • ✓Electrical run from existing board for lights and trickle feed

Value delivered

  • ✓ERT shed delivered to specification, on programme
  • ✓Zero recordable safety events across the works
  • ✓Single contractor for civil, structural and electrical
  • ✓QA documentation handed back at completion
Asset Protection

Burton blast & paint

Ongoing structural blast and paint, in-situ and yard, monthly call-off.

Client / Scope: Blast & PaintLocation: Burton Mine, QLD
Monthly
Call-off scope
8/6
Roster
0/0/0
FAC · MTI · LTI
Follow-on
Awarded

The challenge

  • ✓Live coal-handling assets needing rolling refurb
  • ✓Corroded structural steelwork and coating breakdown
  • ✓Containment of blast media in a live plant environment

The EMS response

  • ✓Encapsulation with brattice to contain media and dust
  • ✓Abrasive blast of structural steel and crusher components
  • ✓Inspect, mark-up and repair defective steelwork
  • ✓Apply protective coating system to spec — EMS-owned plant on site

Value delivered

  • ✓Coal-handling asset life extended
  • ✓Zero recordable safety events across the works
  • ✓Encapsulation kept media and dust off live plant
  • ✓Repeat blast and paint scopes awarded
Buildings & Installs

Grosvenor bathhouse install

Install-only scope on a live site. Civil, structural, plumbing and fit-off.

Client / Scope: Bathhouse InstallationLocation: Grosvenor Mine, QLD
Live site
No shutdown
95 posts
+ 64Lm walkway
0/0
MTI · LTI
Follow-on
Awarded

The challenge

  • ✓Footprint sat over live underground services
  • ✓Fire main needed relocating to AS spec
  • ✓Multi-trade scope, single contractor
  • ✓Inclement weather across the build

The EMS response

  • ✓Hydro-ex to locate live services
  • ✓Fire main relocated outside footprint
  • ✓95 posts and PFC supports installed
  • ✓Modules craned in and fitted off; plumbing and fire connections completed

Value delivered

  • ✓Bathhouse delivered and operational
  • ✓Zero recordable safety events
  • ✓Single contractor across all trades
  • ✓QA pack and engineer sign-offs handed back
Recovery & Vac

Vacuum excavation services

Brand-new mining-spec fleet, ready to deploy across Queensland.

Client / Scope: Vacuum ExcavationLocation: Paget, Mackay, QLD
24/7
Response
Brand-new
Fleet
Mining-spec
Compliant
2006
In market since

The challenge

  • ✓Non-destructive digging around live services
  • ✓Safe and efficient service location
  • ✓Liquid-waste pump out and removal

The EMS response

  • ✓Industrial cleaning of plants and sites
  • ✓Sump and pit cleaning — mining and ports
  • ✓Conveyor and processing area clean-downs
  • ✓Trained crews mobilised from Mackay base

Value delivered

  • ✓24/7 emergency callout — spill response and clean-up
  • ✓Hazardous waste handling and containment
  • ✓Suited to mining, ports and rail sites
  • ✓Trusted by industry since 2006
Civil & Concrete

Shaft cap lowering

Shaft cap demolished and a slab poured for the new rail to run over the top.

Client / Scope: Shaft Cap Demolition & SlabLocation: Moranbah North Rail Diversion, QLD
43m³
Concrete removed
24m³
Stabilised sand
500kg
Steel liner removed
7m³
Concrete poured

The challenge

  • ✓No as-constructed drawings to work from
  • ✓Unknown steel and concrete quantities in the cap
  • ✓Concrete strength not as planned
  • ✓16 m subsidence within the shaft

The EMS response

  • ✓18 m³ steel fibre and 25 m³ mass fill concrete broken out
  • ✓Shaft backfilled with 24 m³ of stabilised sand
  • ✓2 m of 1.5 m dia shaft liner cut and removed
  • ✓4 x 4 x 0.45 m slab formed and poured over the shaft

Value delivered

  • ✓Cap lowered, slab aligned with the new rail network
  • ✓Quick problem solving kept the job on schedule
  • ✓Client kept informed daily and involved in decisions
  • ✓As-constructed drawings handed to the client
Civil & Concrete

South Curragh drainage

Ongoing drain clearing and unblocking to keep wash plant water flowing.

Client / Scope: Drainage ClearingLocation: South Curragh CHPP, QLD
800m
Drains cleared
200t
Coal removed
200m
Bund reinstated
600m²
Pad cleared

The challenge

  • ✓Coal build-up blocking CHPP drains
  • ✓Vehicle and plant interactions
  • ✓Working in with scheduled shutdowns
  • ✓Uneven ground, hard-to-reach places

The EMS response

  • ✓Inspect and plan excavation works
  • ✓Remove coal build-up from the drains
  • ✓Reinstate bunds, redirect water flow
  • ✓Clear drainage beds and consolidate spoil piles

Value delivered

  • ✓Wash plant water flowing as intended
  • ✓Water and coal spoil removed from CHPP infrastructure
  • ✓Water basins ready for the wet season and heavy rain
  • ✓Scope ongoing since August 2026
Asset Protection

CHPP spoil removal

Coal spoil and nib wall removal with the wash plant running.

Client / Scope: Spoil & Nib Wall RemovalLocation: South Curragh CHPP, QLD
~4,700m³
Spoil removed
45m
Nib wall removed
Full floor
Wash plant one
Full floor
Crusher

The challenge

  • ✓Spoil build-up limiting crew access
  • ✓Nib walls restricting cleaning
  • ✓Machinery in very tight spaces
  • ✓Multiple moving parts close by

The EMS response

  • ✓~4,700 m³ of coal spoil removed
  • ✓45 m of nib wall demolished
  • ✓Drainage paths restored to stop water pooling
  • ✓Areas around conveyors and crushers cleaned

Value delivered

  • ✓No disruption to production
  • ✓Safe access for maintenance and inspection crews
  • ✓Faults show up sooner with less build-up
  • ✓Scope ongoing since April 2026